PMI Risk Management Professional (PMI-RMP)® — Question 134
PMI RMP Part 7 · question 134 of 197 in the PMI Risk Management Professional (PMI-RMP)® question bank. Pick an answer to check it, or join the discussion below.
Question 134 (Q136)
While managing a complex construction project with multiple stakeholders and a tight schedule, a critical risk is identified where severe weather could delay timelines in the schedule and increase the overall costs. The risk manager proposes several risk responses. Which action will provide an effective risk response strategy to minimize the impact of this risk?