Question 126 (Q128)
The planning phase of a construction project in a busy urban area IS underway. The risk manager identifies conditions such as the availability of skilled labor, an uninterrupted supply of materials, and favorable weather. The project also faces constraints, including a fixed budget, strict environmental regulations, and a six-month timeline for completion. Midway through the project, a newly elected city mayor introduces additional environmental requirements, posing risks of potential delays and increased costs.
What should the risk manager do?