Question 123 (Q125)


A risk manager is part of a team overseeing a renewable energy project that involves multiple contractors and strict environmental regulations. During risk planning, the team identifies several risks related to equipment malfunctions and environmental impact violations. However, the contractors have varying interpretations of what constitutes a significant risk, and the regulatory body has not provided clear guidelines.
What should the risk manager do?