PMI Risk Management Professional (PMI-RMP)® — Question 123
PMI RMP Part 7 · question 123 of 197 in the PMI Risk Management Professional (PMI-RMP)® question bank. Pick an answer to check it, or join the discussion below.
Question 123 (Q125)
A risk manager is part of a team overseeing a renewable energy project that involves multiple contractors and strict environmental regulations. During risk planning, the team identifies several risks related to equipment malfunctions and environmental impact violations. However, the contractors have varying interpretations of what constitutes a significant risk, and the regulatory body has not provided clear guidelines.
What should the risk manager do?