Question 120 (Q122)


During project to upgrade IT infrastructure, a key decision-maker expresses willingness to accept budget overruns to ensure high-quality results. However, the finance department has a low tolerance for exceeding budgetary limits. The risk manager must confirm the project’s risk thresholds to finalize the risk management plan. How should the risk manager address the stakeholders’ varying risk appetites?