Question 118 (Q120)


A newly appointed risk manager is assigned to project halfway through the development stage. Upon review, the risk manager notices that a previous project response to a suppliers delay resulted in additional challenges for the project team, causing further disruptions. Additionally, minor quality concerns arise due to the supplier’s timeline readjustment. What should the risk manager do?