Question 100 (Q102)


A risk manager is conducting a qualitative risk analysis for a large-scale infrastructure project. The identified uncertainties include labor shortages, unpredictable weather conditions, and equipment breakdowns. Team members disagree on prioritization. Some argue for focusing on high-likelihood concerns, while others stress the importance of addressing low-probability but high-impact scenarios, such as prolonged regulatory delays.
What should the risk manager do?