PMI Construction Professional (PMI-CP) — Question 97
PMI CP Part 5 · question 97 of 120 in the PMI Construction Professional (PMI-CP) question bank. Pick an answer to check it, or join the discussion below.
Question 97
A project has a large number of claims due to lack of alignment and misinterpretation of expectations with the approved project scope. It seems that each project entity has its own sources of documentation and evaluation criteria. What should the construction professional do to resolve this situation?