Question 95


A construction management firm is starting a new contract for a large project. The owner of the project is a long-term client and they have completed similar projects in the past with the construction management firm. The owner is risk averse but has a high level of confidence in the organization to design and construct this project successfully with minimum input from the owner.
Which delivery method should the construction professional propose?