PMI Construction Professional (PMI-CP) — Question 91
PMI CP Part 5 · question 91 of 120 in the PMI Construction Professional (PMI-CP) question bank. Pick an answer to check it, or join the discussion below.
Question 91
A delay in the handover date of a retail unit occurred due to the late delivery of a long-lead item. The commercial department complains to the construction professional that they cannot understand the real impact of the delay from the weekly technical report the construction professional sent to all stakeholders. What should the construction professional have done differently to manage the communication with the commercial department?