PMI Construction Professional (PMI-CP) — Question 88
PMI CP Part 5 · question 88 of 120 in the PMI Construction Professional (PMI-CP) question bank. Pick an answer to check it, or join the discussion below.
Question 88
An oil and gas company was awarded a new project to build a liquefied natural gas (LNG) plant in a high-risk industrial area. Due to the nature and location of the project, the company tries to leverage a technology that will help with scoping the project, on-site progress monitoring, and data collection. Which technology should the construction professional suggest the company use to achieve its goals?