Question 83


A large government project that involves multiple interface points is at the beginning of the implementation stage, and the main construction contractor has been awarded their contracts. A weekly progress meeting was scheduled to involve all relevant personnel. During one of those meetings, one of the interface stakeholders asked the construction professional how they intend to implement a specific feature for which this interface stakeholder is responsible. The construction professional is surprised by the question and cannot provide the interface stakeholder with an adequate response.
What should the construction professional have done to prevent this from happening?