PMI Construction Professional (PMI-CP) — Question 77
PMI CP Part 4 · question 77 of 120 in the PMI Construction Professional (PMI-CP) question bank. Pick an answer to check it, or join the discussion below.
Question 77
During the execution of a large construction project, the contractor’s team proposed changes related to the sequencing of some critical activities to help reduce cost and the time required to accomplish those specific activities. Who should be responsible for assessing the raised changes, evaluating their impact, and deciding whether to accept or reject the proposed changes?