PMI Construction Professional (PMI-CP) — Question 73
PMI CP Part 4 · question 73 of 120 in the PMI Construction Professional (PMI-CP) question bank. Pick an answer to check it, or join the discussion below.
Question 73
A development organization received a change order from a general contractor managing one of their high-profile projects. The contracts manager for the developing organization delegated the task of evaluating the potential change order to a new hire who has recently graduated. The new employee reaches out to the construction professional for advice about which areas the potential change order should be evaluated across.
Across which three areas should the construction professional advise the potential change order be evaluated? (Choose 3)