PMI Construction Professional (PMI-CP) — Question 66
PMI CP Part 4 · question 66 of 120 in the PMI Construction Professional (PMI-CP) question bank. Pick an answer to check it, or join the discussion below.
Question 66
A construction project involves procuring several elevators. At the contract signing, the elevator supplier emphasized that lead times are going to be long. During the implementation phase, the construction professional calls the supplier to order the elevators. The supplier informs the construction professional that the elevators will arrive on-site 5 weeks later than originally planned.
What should the construction professional have done to prevent this from happening?
Checking access…

Discussion
Loading comments…