PMI Construction Professional (PMI-CP) — Question 60
PMI CP Part 3 · question 60 of 120 in the PMI Construction Professional (PMI-CP) question bank. Pick an answer to check it, or join the discussion below.
Question 60
A construction professional is part of a large project where contractors complete different project packages in the same development project. The construction professional’s project, package A, has several interfacing points with another contractor’s project, package B, but no direct contractual relationship exists between them. During an interface meeting, the construction professional learns that package A will need to be completed within an 8-week window to allow package B’s work to continue and meet the milestone date. The construction professional holds an internal team meeting and concludes that the work can realistically be completed within 10 weeks. The construction professional presents this counteroffer in the next interface meeting with the package B team and the project developer.
Which specific commitment-based management (CbM) framework did the construction professional employ in this negotiation?
Checking access…

Discussion
Loading comments…