PMI Construction Professional (PMI-CP) — Question 57
PMI CP Part 3 · question 57 of 120 in the PMI Construction Professional (PMI-CP) question bank. Pick an answer to check it, or join the discussion below.
Question 57
An international construction firm with a matrix organizational structure just completed a challenging build project. During the project closeout meeting, lessons learned were discussed and documented. Many of the challenges in the project were caused by functional managers making localized decisions and providing conflicting requirements to their subordinates, resulting in a significant amount of rework and cost to the organization.
What should the construction professional advise the firm to do to avoid this situation in future projects?
Checking access…

Discussion
Loading comments…