Question 55


A contractual dispute occurs between a member of the constructional professional’s team and one of the project’s subcontractors. The subcontractor claims that the construction professional’s company should provide some site mobilization items such as temporary lighting for safety and water supply for the construction activities. In previous projects, all of these were supplied by subcontractors. The construction professional assumed this project would be the same but, upon checking the subcontract documents signed by both companies, they discovered the subcontractor was right.
What should the construction professional have done to prevent this communication gap?