Question 52


A construction professional discovers that the design drawings show the entry doors opening in the wrong direction, affecting the position of electrical switches. The construction professional can rectify this issue immediately on-site but decides to consult the client for a final decision. The client not only agrees to the proposed change, but also adds an additional electrical switch because the design department discovered that this can increase usability.
This is an example of what?

Checking access…

Discussion

Loading comments…

← Back to question bank