Question 38
A construction professional is developing a stakeholder analysis matrix for a construction project to deliver a new school. The project sponsor may be promoted to a new role and the school principal is on leave. One of the teachers is acting as the client’s liaison for the principal. What communication approach should the construction professional use with the project sponsor?