PMI Construction Professional (PMI-CP) — Question 32
PMI CP Part 2 · question 32 of 120 in the PMI Construction Professional (PMI-CP) question bank. Pick an answer to check it, or join the discussion below.
Question 32
A main contractor is in the execution phase of a food processing factory on a design-bid-build (DBB) lump sum contract. The ovens, supplied by the owner, are interfering with the overhead utilities and the contractor is raising a claim for extra cost and time. What should the construction professional do first while assessing the claim?