A construction professional recently joined a complex construction program. The construction professional is informed that the client is unhappy with the project’s progress, and that no follow-up action was taken on previously identified problems. The construction professional also observes that team members are neither engaged nor are they collaborating in discussions during meetings. Additionally. the construction professional realizes that the project information has not been updated on the visual boards.
What should the construction professional have done to foster effective engagement, communication, and collaboration among all cross functional team members?