PMI Construction Professional (PMI-CP) — Question 24
PMI CP Part 2 · question 24 of 120 in the PMI Construction Professional (PMI-CP) question bank. Pick an answer to check it, or join the discussion below.
Question 24
The main contractor for a project to construct a new hotel is in the execution phase of a design-build (DB) lump sum contract. The client delayed approval of some room features, so the contractor raised a claim for extra time. What should the construction professional representing the client do first while evaluating the claim?