Question 22


A real estate development firm is working on defining the scope of work for a project to build a modern resort. The time line is tight and shareholders are pushing for the bid to be issued. The construction professional recommends involving all stakeholders in the scope definition exercise; however, the project sponsor insists on involving only the project team to expedite the process.
What should the construction professional do next?