PMI Construction Professional (PMI-CP) — Question 16
PMI CP Part 1 · question 16 of 120 in the PMI Construction Professional (PMI-CP) question bank. Pick an answer to check it, or join the discussion below.
Question 16
A construction project to build a mixed commercial-residential development is in the planning phase. The project has many stakeholders and multiple communications channels. The construction professional analyzes stakeholders and has identified one stakeholder who has high interest in the project but low influence, so the construction professional decides to exclude this stakeholder from any project communications to reduce the number of communications channels.
What will be the predicted outcome of the construction professional’s decision?