Question 14


During a retrospective meeting for one of the build projects, the team identifies areas of improvement and strength. The construction professional commends the team for effectively mitigating multiple claims, because the contract specifications were clear and well-defined, schedule requirements were clear and realistic, and there was a request for information (RFI) procedure in place.
What contributed to the success of this project?