PMI Construction Professional (PMI-CP) — Question 114
PMI CP Part 6 · question 114 of 120 in the PMI Construction Professional (PMI-CP) question bank. Pick an answer to check it, or join the discussion below.
Question 114
A construction professional is assigned to a large construction project to build outlets for high-end brands The project has multiple interfaces among different disciplines, subcontractors, and key stakeholders. Throughout the project, the construction professional served as a project liaison between different parties, reviewed and approved interface requests, and successfully provided interface support when needed.
Which role did the construction professional serve on this project?