Question 111


A project manager was assigned to a project to build a commercial port. During the planning phase, the construction professional proposed performing value engineering (VE) but the project manager refused as this will delay the design, and construction should start as soon as possible. However, the project manager promises to look into this during the construction phase when productivity stabilizes.
What should the construction professional do next?