Question 105


A construction professional is executing a project to construct a residential building. The project is on schedule and within budget. Midway through the project, the construction professional receives a notification from the government’s environmental department indicating that the project should be paused as it is missing an environmental permit. It will take 4 weeks for the permit to be approved, causing major project delays.
What should the construction professional check first to determine how this problem occurred?