Question 103


A construction professional is assigned to a large, complex, and high-profile construction project with many stakeholders and numerous interface points. The client would like the construction phase to begin as soon as possible. In an attempt to expedite planning, the construction professional decides to complete the communications management plan immediately after identifying stakeholders and utilizes communications management plans from past, similar projects for communications requirements. Three months into construction, many stakeholders are frustrated with the large number of communications they receive, whereas other stakeholders complain that they do not receive the communications they need. The project is being negatively impacted by this situation.
What should the construction professional have done to avoid this situation?

Checking access…

Discussion

Loading comments…

← Back to question bank