A project manager is evaluating whether an Al model is ready for operationalization. The project team has ensured the model meets accuracy and performance requirements and has conducted extensive testing. However, uncertainty about the model’s operationalization in different environments and its compliance with regulatory standards still exists. What should the team do next?