PMI Agile Certified Practitioner (PMI-ACP)® — Question 90
PMI ACP Part 5 · question 90 of 140 in the PMI Agile Certified Practitioner (PMI-ACP)® question bank. Pick an answer to check it, or join the discussion below.
Question 90
During backlog refinement, the team uses an online planning poker tool for estimation. The junior developers change their number of story points after they see the estimations provided by the senior developers. The junior developers state that the reason for this is that they do not have enough experience and do not want to be blamed for sizing it wrong. What should the scrum master do?