PMI Agile Certified Practitioner (PMI-ACP)® — Question 72
PMI ACP Part 4 · question 72 of 140 in the PMI Agile Certified Practitioner (PMI-ACP)® question bank. Pick an answer to check it, or join the discussion below.
Question 72
An agile practitioner is working on a project to migrate data from computer systems to another location. To accomplish this task, they need to run four activities sequentially that different teams are performing. The teams are migrating two systems per day, but the agile practitioner thinks that three systems should be done per day. What can be done to improve process efficiency?
Checking access…