PMI Agile Certified Practitioner (PMI-ACP)® — Question 51
PMI ACP Part 3 · question 51 of 140 in the PMI Agile Certified Practitioner (PMI-ACP)® question bank. Pick an answer to check it, or join the discussion below.
Question 51
A development team is calculating the number of story points they have completed at the end of an iteration. Although quality assurance (QA) passed and successfully demonstrated one feature, it is not being included in the release package. Should the team add the feature’s story points to their burndown chart?