Question 36☆ In Scrum, the responsibilities of the project manager are shared among the product owner, scrum master, and development team: Why are responsibilities shared among the three roles?
A. The product owner is responsible for the product and sprint backlog. The serum master follows up on progress. and the development team estimates and decomposes the backlog items into manageable pieces. This ensures each person has the roles they are best at and feel most comfortable with B. Scrum is a collaboration frameworks that encourages the Scrum team-the product owner. Sorum master, and development team-to collaborate in a way that fosters fast value creation with respect for each learn member’s opinions and individual preferences. C. The product owner is responsible for the product backlog and long-term plans. the scrum master is responsible for the Scrum process, and the development team is responsible for the sprint backlog and progress toward the sprint goal. This facilitates clear accountability and effective value creation. D. “Inspect and adapt” are two of the three pillars ip Scrum. The roles in Scrum are divided among the product owner. scrum master: and development team in a way that makes it possible to inspect the efficiency and adapt the way responsibilities are shared to maximize efficiency if needed. Checking access…
← Previous question 36 of 140 Next question → ← Back to question bank
Discussion
Loading comments…