Question 30


As part of the organizational change, all project teams within the digital channels portfolio have been directed to move from 3-week iterations to 2-week iterations. The development team is frustrated as they think there will not be enough time to test. The product owner does not like this change as it will increase the number of ceremonies. Which two actions should the scrum master take? (Choose 2)