Question 12
A Scrum team decided to switch to Kanban for the maintenance phase of the product. The kanban board consists of the following columns: “To do,” “in progress,” “Ready to be tested,” “Test in progress,” and “Done.” Since the team changed their way of working, they have noticed the work is flowing slower in the system. A large queue of “Ready to be tested” work items has been building up.
What should the team do to improve its speed of delivery?