PK0-005 CompTIA Project+ Certification Exam — Question 87
Pk0 005 Part 5 · question 87 of 199 in the PK0-005 CompTIA Project+ Certification Exam question bank. Pick an answer to check it, or join the discussion below.
Question 87
A project owner notified a project manager that a 15% bonus will be paid if the project is completed three weeks earlier than initially planned without incurring additional cost. Which of the following best describes what the project manager should do?