PK0-005 CompTIA Project+ Certification Exam — Question 59
Pk0 005 Part 3 · question 59 of 199 in the PK0-005 CompTIA Project+ Certification Exam question bank. Pick an answer to check it, or join the discussion below.
Question 59
During the execution of a project, three employees who were recommended to work on an upcoming phase resigned from the company. Which of the following should the project manager do first?