Question 45


During the lessons learned session, a project manager received feedback from the team about not having a clear understanding of the information flow throughout project phases. The team also mentioned that meetings were unplanned and sometimes disruptive. Which of the following best describes what the project manager should have done during the planning phase to avoid these issues?