ITIL 4 Specialist: Drive Stakeholder Value — Question 46
Itil 4 Specialist Drive Stakeholder Value Part2 2 · question 46 of 60 in the ITIL 4 Specialist: Drive Stakeholder Value question bank. Pick an answer to check it, or join the discussion below.
Question 46
A development team has received several sets of requirements for a new software application that share a similar priority. They wish to use the weighted shortest job first’ method to decide which job to develop first. They have calculated a development time for each job, and a cost of delay that takes into account service impact, urgency and risk.
Which should they develop first?