ITIL 4 Practitioner: Continual Improvement — Question 16
Itil 4 Practitioner Continual Improvement 2 · question 16 of 20 in the ITIL 4 Practitioner: Continual Improvement question bank. Pick an answer to check it, or join the discussion below.
Question 16
An organization is concerned about the lack of participation in continual improvement activities. It has received the feedback that it takes too long for ideas to be approved and implemented.
What is the BEST action for the organization to take to improve this situation?
What is the BEST action for the organization to take to improve this situation?