Question 42 (Q47)


To reduce the configuration workload of the network administrator, an enterprise deploys a service system in the computing scenario of Huawei CloudFabric Solution. After receiving service requirements from the department, the administrator performs the following steps to provision services:
1. Add hosts to FusionCompute and create a distributed virtual switch.
2. Create VMM mappings to generate a port group for the distributed virtual switch.
3. Select a host and create VMs.
4. iMaster NCE-Fabric detects VM login and automatically delivers port and gateway configurations.
5. Create tenants and VPCs on iMaster NCE-Fabric and create logical networks in the VPCs. Which of the following is the correct order of these steps?