H12-425 HCIP-Data Center Facility Deployment — Question 69
H12 425 Part 4 · question 69 of 91 in the H12-425 HCIP-Data Center Facility Deployment question bank. Pick an answer to check it, or join the discussion below.
Question 69 (Q78)
A UPS5000-E-200K is configured with two 200 Ah battery strings. Each battery string consists of forty 12 V batteries. What is the capacity of battery strings connected to the UPs?