Question 71 (Q72)


The manager of a key project has bypassed the standard contractor onboarding process to acquire additional resources for delivering the project on time. Contracts were executed offline, and contractors were provided organizational access without going through the standard due diligence process. Which of the following should be the PRIMARY concern?