CAPM Certified Associate in Project Management — Question 59
PMI CAPM Part 3 · question 59 of 200 in the CAPM Certified Associate in Project Management question bank. Pick an answer to check it, or join the discussion below.
Question 59
An adaptive team’s velocity dropped significantly in the last sprint due to the planned vacation of two team members The project sponsor wants to know how many more sprints it would take to complete the remaining project. How should the project manager calculate the anticipated velocity for future sprints?