CAPM Certified Associate in Project Management — Question 50
PMI CAPM Part 3 · question 50 of 200 in the CAPM Certified Associate in Project Management question bank. Pick an answer to check it, or join the discussion below.
Question 50
A project team has completed the first iteration and the testing manager approved the test report, indicating that the acceptance criteria have been met. The manager of the business unit that will use the new product is asking for additional functionality before approving the rollout for their team. What should the project manager do next?