CAPM Certified Associate in Project Management — Question 166
PMI CAPM Part 9 · question 166 of 200 in the CAPM Certified Associate in Project Management question bank. Pick an answer to check it, or join the discussion below.
Question 166
Calculate the cost variance, given the following: EV = 19 and AC = 23