Question 162


A network operations team has a project to develop a network automation solution. The team organizes the project into a series of iterations that break down the large, complex project into smaller, manageable tasks. The team structures its quick daily meetings around three questions.
1. What did I work on yesterday?
2. What am I working on today?
3. Which issues are blocking me?
Which project management methodology is the team using?